13 December 2020 Procurement of the dome and the telescope structure of the ELT: update status report
Stefano Stanghellini, Pascal Martinez, Maximilian Kraus
Author Affiliations +
Abstract
The telescope Main Structure and the Dome of the ELT are being procured by ESO as an integrated system together with the auxiliary building and the service plants, and are supplied by the ACe Consortium. From the start of the contract, signed in May 2016, major progress has been achieved. During the design phase various challenging technical issues had to be solved, not least given the size of the ELT and the environmental conditions at Cerro Armazones in Chile. As per today the system has been developed, detail designed, reviewed, and is completing the Final Design Review process. Procurement of long lead or schedule critical items was assured by using specific Critical Design Reviews. Manufacturing in Europe and construction in Chile have started and are proceeding, although delays were encountered due to various issues including the Covid-19 pandemic. In this paper we will describe the advancement reached by the project and discuss some technical aspects associated to the design. The status of the design, of the manufacturing and of the construction on site will be described.
Conference Presentation
© (2020) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
Stefano Stanghellini, Pascal Martinez, and Maximilian Kraus "Procurement of the dome and the telescope structure of the ELT: update status report", Proc. SPIE 11445, Ground-based and Airborne Telescopes VIII, 114450B (13 December 2020); https://doi.org/10.1117/12.2562246
Advertisement
Advertisement
RIGHTS & PERMISSIONS
Get copyright permission  Get copyright permission on Copyright Marketplace
KEYWORDS
Telescopes

Manufacturing

Buildings

Design for manufacturability

Mirrors

Optical instrument design

Prototyping

RELATED CONTENT

ZERODUR iso grid design of a 3m class light weighted...
Proceedings of SPIE (July 18 2014)
Design and MAIT status of the UH2.2 adaptive secondary mirror
Proceedings of SPIE (December 13 2020)
Designing the primary mirror support for the E-ELT
Proceedings of SPIE (August 08 2016)
Design of the Discovery Channel Telescope enclosure
Proceedings of SPIE (September 28 2004)
Manufacturing optics of a 2.5m telescope
Proceedings of SPIE (September 17 2012)

Back to Top